    Hi Will,

    Thank you for your Forum submission.  We look forward to assisting you with your request.  Due to the increased volume and demand on our economists, you may experience a longer response time that optimal.  We will answer your questions in the order in which they were received.  If you need a more prioritized response, we do offer dedicated time with our economists at $225 per 30 minutes and this can be accommodated within 24 hours of your request, during standard business days.  Please contact your Customer Success Manager to schedule this or email Info@implan.com.

    We have recently improved and updated our support site, please visit here to more easily search previous forum posts and responses, articles and other related content.

    Thanks,

    IMPLAN Staff

    0
    Comment actions Permalink
  • Avatar
    IMPLAN Forum

    Hi Will,

    Thank you for your patience while we worked on your post. In order to model for demolition costs, we recommend Analysis-by-Parts (ABP) methodology where you can import a construction sector and modify the coefficients to reflect the usage of commodities appropriately. For example: if you think you may not need commodities like concrete, you can zero it out OR reduce the coefficient to reflect the correct amount of concrete that's being used. To learn more about ABP, please click HERE.

    As a side note, the response from 4 years ago on IMPLAN Forum is still relevant if in case you would like to use it as a reference.